<< Click to Display Table of Contents >> Cost components |
1.In the menu bar, select Administration > Codelists > Codelist manager.
2.Select DSG in the Codelist Owner field.
3.Select CALC_PROC_PARAM_CL in the Codelist field.
4.Press Add .
5.Select the parameters that you would like to apply.
6.Press Save.
It is possible to have a maximum of eight values on the first axis, for example High voltage, Low voltage and substation. It is possible to have a maximum of three values on the second axis, for example Investment and Maintenance. |
In the module Investment KPI, it is possible to set up distribution parameters in cost catalogs so that each cost is created automatically on the correct category in the calculation. This can be done for an existing cost catalog by exporting it as type… with dynamic parameters and depreciation time. The last columns in this file indicates which parameter that will carry the cost. For example, if there is a cost that is to be marked as an investment, the value 100 (corresponds to 100%) is set in this column. |