Create a Call activity

<< Click to Display Table of Contents >>

Organizer > Process Automation > Model a Process >

Create a Call activity

A Call activity is used in a main process to link to a sub-process.

 

1.In the Create tab, select Call activity and press Place object or double-click.

2.Optionally, set a Name and Description.

In the fields Estimated duration, days and hours, you specify how long the call activity is expected to take. When the process is linked to a task in Organizer, the specified time will be displayed as the planned start and end time of the activity.

3.To link to a process, press Search process in the Process reference section.

4.Search for the desired process and press OK.

5.Press OK.

6.Place the call activity in the process illustration. A sub-process is now linked to the main process via the call activity.

 

Show the sub-process

The sub-process is not displayed in the same window as the main process but can be displayed in a separate view.

1.Right-click on the call activity and select Show sub-process and select a view:

oShow in active view

oShow in other view

oShow in new window