SUSIE

<< Click to Display Table of Contents >>

Operator >

SUSIE

To access the SUSIE function in the Operator menu, a license is required.

The SUSIE function (Samverkan under störning inom elförsörjning = Collaboration during disturbances in electricity supply) means that at specific time intervals, outage information is sent to a central location for further processing/reporting by Svensk Energi.

The information includes reporting of the following by municipality:

Municipality code.

Number of power outage customers.

Start time for the first initiated outage within the municipality.

Expected completion time for the outage within the municipality that is estimated to be resolved last.

Whether the outage/outages occurred in the own network, the upstream network, or a combination of both.

If at least one of the outages is a disturbance, type Disturbance should be reported, otherwise, Planned.

Total number of customer facilities within the municipality.

 

You can select from these submenus:

Send update to SUSIE - Verifies whether the transmission was successful or unsuccessful, along with information about each update.

Show JSON (for debugging) - Shows what is actually sent to SUSIE.