<< Click to Display Table of Contents >> Milestone |
The Milestone function handles the tasks phases and important events in the form of milestones. Unlike activity and decision point, a milestone only has a planned/actual date.
1.In the east panel, select the Workflow tab.
2.Press Add object and select New milestone
. The dialog Select milestone type opens.
3.Select a milestone type and press OK.
The milestone type can not be edited. |
4.Fill in the desired information and dates:
oSort value - A sort value set to 1 will appear at the top of the listed activities. The sorting value can also be found in the query tool.
oOwner - Press to Take activity
so that you become the owner, or Select owner
to select someone else as the owner.
For milestones that have ever been owned by an inbox, you can select Restore the previous inbox as owner |
oPlanned date - Fill in planned date .
oDate - Fill in the actual date .
oAlarm - Press to send an email to the owner of the workflow item. Set the number of days before and after the planned start and end dates.
In order for emails to be sent out, scheduled jobs and email templates need to be configured in the customer environment, contact Digpro support for help setting this up. |
5.Press Save.