Complete calculation

<< Click to Display Table of Contents >>

Designer > Calculation >

Complete calculation

Completion of calculation cannot be undone.

When a calculation is completed, you can no longer change, add, or remove costs from it.

1.In the Calculations tab, select a calculation and press Complete calculation . The calculation is moved under the heading Completed and the date of completion is displayed next to the calculation name.

A completed calculation that is deactivated cannot be activated again.

2.To deactivate the completed calculation, press Activate/deactivate calculation .

Completed calculations can be copied, see section Copy calculation and change catalog. The copied calculation ends up under the Ongoing heading and the completion date is not copied.